The Windsor-Detroit Bridge Authority (WDBA) announced that construction completion of the Gordie Howe International Bridge is now planned for September 2025 with the first vehicles expected to travel across the bridge that fall.
Originally, the $5.7 billion (CDN) project was scheduled for completion in November 2024 with opening anticipated by the end of that year.
However, the project, like many others, experienced unprecedented disruptions as a result of the COVID-19 global pandemic. The disruptions were even more prevalent for the Gordie Howe International Bridge project given the differing applicable restrictions in the US and Canada, combined with the ramping up of construction activities in early 2020.
Like most public-private partnerships (P3) contracts, the contract between Windsor-Detroit Bridge Authority (WDBA) and Bridging North America (BNA) provides for the schedule and cost impacts of certain risks to be shared. As a result, WDBA and BNA have agreed to amend the contract to include the new September 2025 construction completion date, new measures to ensure this date is achieved, and an updated overall contract value of $6.4 billion (CDN).
Source: WDBA